Project Description:
This Sampling and Analysis Plan (SAP) provides the scope and methods to evaluate the suitability for open-water disposal of sediments at the I&J Waterway Site (Site) in Bellingham Bay in Bellingham, Washington under the Puget Sound Dredged Disposal Analysis Program (PSDDA) (See site map,
Figure 1-1). This testing is being performed in support of the Sediments
Remedial Investigation and Feasibility Study (RI/FS) occurring at the Site under the oversight of the Department of Ecology (Ecology). The need for disposal is driven by the cleanup at the site, but the design of the remedial activities will be influenced by navigation needs within the waterway and adjacent areas.
Entire report: http://www.ecy.wa.gov/programs/TCP/sites/blhm_bay/sites/I_and_J_Waterway/I&J%20Seds%20RIFS%20App%20B%20Text.pdf